What does it cost? Just an honest overview.
No 'price on request' and no small print. Below you'll find all indicative prices: what you pay us for the installation work, and what the grid operator charges. The exact price for your situation comes upfront — fixed and without obligations.
Installation work (through us)
Indicative prices including installation and VAT. After the intake you receive a fixed price for your situation.
| Work | Indicative price |
|---|---|
| Fuse box replacement (single phase) | from € 649 |
| Fuse box replacement (3-phase) | from € 899 |
| Adding an extra circuit | € 100 – € 250 per circuit |
| Cooking circuit / Perilex connection | € 150 – € 350 |
| Meter cupboard adjustments (layout, ventilation) | indication in the quote |
Grid operator costs (paid directly to the grid operator)
You pay these one-off costs (2026 rates) directly to your grid operator — we earn nothing on them. We help with the application via mijnaansluiting.nl free of charge.
| Service | 2026 rate |
|---|---|
| Upgrade to 3×25A — Liander | € 368.77 |
| Upgrade to 3×25A — Enexis | € 275.15 |
| Upgrade to 3×25A — Stedin | € 258.95 |
| Replacing melt fuse with circuit breaker — Liander | € 635.07 |
| Entirely new 3×25A connection | € 1,661.94 |
Regional grid operators (such as Coteq or Rendo) apply similar rates. We'll find out which grid operator serves your address.
And per year? With 3×25A little changes.
The fixed grid costs depend on the capacity of your connection. The good news: the standard 3-phase connection costs virtually the same per year as what you probably pay now.
All amounts mentioned are indications based on common situations and the 2026 grid operator rates. After the intake you receive a fixed price for your situation — and we stick to it. No hidden costs, no surprises afterwards.